| 2026/05/21 Installed new power supplies to Radar1 | 2026/05/21 Installed new power supplies to Radar1 | ||
| - | 2026/05/21 Radar 2 brough | + | 2026/05/21 Radar 2 brought |
| 2026/05/27 problem connecting to RVP8 determined to be a boot issue, connected a monitor and keyboard to RVP8, and determined it was having difficulty connecting to hard drive. Reseated hard drive ribbon cable, boot sequence now works as intended. When keyboard is connected, requires key input at power on and pressing esc to boot before beginning sequence. | 2026/05/27 problem connecting to RVP8 determined to be a boot issue, connected a monitor and keyboard to RVP8, and determined it was having difficulty connecting to hard drive. Reseated hard drive ribbon cable, boot sequence now works as intended. When keyboard is connected, requires key input at power on and pressing esc to boot before beginning sequence. | ||
| Line 11: | Line 11: | ||
| 2026/06/02 New 10ASB fuse was fitted into Mod Voltage. Fuse was heated to the point of melting the solder, indicating a short somewhere in the Radar electronics. | 2026/06/02 New 10ASB fuse was fitted into Mod Voltage. Fuse was heated to the point of melting the solder, indicating a short somewhere in the Radar electronics. | ||
| + | 2026/06/09 Mod voltage fuse light had a loose connection, causing the fuse to melt, radar still not operating after fix. Currently assumed to be an issue with the magnetron or pulse package. | ||
| + | 2026/06/15 radarpi setup in CH601, radar2 is now connected to the internet and is able to be connected to via terminal. At the moment, data will have to be processed and displayed on the connected computer. | ||
| + | |||
| + | 2026/06/17 Rack in CH601 was rearranged to fit new transmitter assembly. The UPS was moved up to directly below the RCP8, and the new Transmitter assembly was installed below that. A few mounting brackets were removed that were not put back, and the old Azimuth/ | ||
| + | |||
| + | 2026/06/18 Some cable management was done to organize and understand the connections between the cabinet, the RCP8, the Azimuth/ | ||